HWC CDU Network Upgrade – Delivery Bunds and Dosing Points

Client: Hunter Water Corporation

Construction of delivery bunds and dosing points 11 Principal sites across the Hunter Region.

Excavations and earthworks including access construction

Demolition of any existing concrete structures and removal of rubble to approved waste facility.

Supply and Install of concrete slab materials

Concrete placement and finishing

Supply and install of handrails

Supply and connection of drain from bund sumps 

Construction of retaining walls 

Our Accreditations

TCM has achieved third party certification for our Business Management System which comprises of the International and Australian Standards in ISO 9001:2015 Quality Management Systems, ISO 45001:2018 Occupational Health and Safety Management Systems and ISO 14001:2015 Environmental Management Systems.

More Posts

Southern Arm Trunk Main

Client: Port Macquarie-Hastings CouncilLocation: Houston Mitchell Drive, Lake Cathie, NSWProject Duration: January 2024 – October 2024 The Southern Arm Trunk Main project involves the installation of a 5.7

Figtree Watermain Renewal Program

Client: Upper Hunter Shire CouncilLocation: Murrurundi, Scone and Merriwa NSWProject Duration: April 2023 – January 2024 Supply and Construction of a new DN100 to DN200 PVC-M / DICL