Lake Macquarie City Council
Part of the expansion of the Awaba Waste Management Facility. TCM was contracted to construct
- 3,412 m of DN140/DN90 HDPE rising main
- Install two new DN160 gravity incoming lines
- 1.2m x 1.2m x1.2m flowmeter/dosing pit with trafficable lid and flowmeter
- 1.2m diameter actuated valve chamber
- 1.8m diameter package pump station with integral valve 80mm nominal diameter discharge pipework, valves and fittings