Clarence Town Wastewater Transportation System

Hunter Water Corporation

Completion of remaining works outstanding under terminated contract of former contractor for the construction of Clarence Town wastewater transportation system.

Construction of sewer gravity system.
Construction of 2 wastewater pump stations
Construction of sewer rising mains.

Many challenges were faced after the termination of the previous contractor. Community liaison was paramount to ensure the township of a speedy and professional completion to the project.

After completion of the remaining pipeline and two pump stations, many faults and leakages were found in the sections the previous contractor had constructed that had to be repaired. TCM completed this project with the client and community satisfied with the outcome.

Our Accreditations

TCM has achieved third party certification for our Business Management System which comprises of the International and Australian Standards in ISO 9001:2015 Quality Management Systems, ISO 45001:2018 Occupational Health and Safety Management Systems and ISO 14001:2015 Environmental Management Systems.

More Posts

Southern Arm Trunk Main

Client: Port Macquarie-Hastings CouncilLocation: Houston Mitchell Drive, Lake Cathie, NSWProject Duration: January 2024 – October 2024 The Southern Arm Trunk Main project involves the installation of a 5.7

Figtree Watermain Renewal Program

Client: Upper Hunter Shire CouncilLocation: Murrurundi, Scone and Merriwa NSWProject Duration: April 2023 – January 2024 Supply and Construction of a new DN100 to DN200 PVC-M / DICL

Send Us A Message