Clarence Town Wastewater Transportation System

Hunter Water Corporation

Completion of remaining works outstanding under terminated contract of former contractor for the construction of Clarence Town wastewater transportation system.

Construction of sewer gravity system.
Construction of 2 wastewater pump stations
Construction of sewer rising mains.

Many challenges were faced after the termination of the previous contractor. Community liaison was paramount to ensure the township of a speedy and professional completion to the project.

After completion of the remaining pipeline and two pump stations, many faults and leakages were found in the sections the previous contractor had constructed that had to be repaired. TCM completed this project with the client and community satisfied with the outcome.

Our Accreditations

TCM has achieved third party certification for our Business Management System which comprises of the International and Australian Standards in ISO 9001:2015 Quality Management Systems, ISO 45001:2018 Occupational Health and Safety Management Systems and ISO 14001:2015 Environmental Management Systems.

More Posts

Muswellbrook Pipe Renewal Program

Client: Muswellbrook Shire Council Installation of 1.2km of DN100 PVC-O Pipeline including fittings Installation of 220m of DN150 PVC-O Pipeline including fittings Installation of 90+

Send Us A Message