Gunnedah to Curlewis Pipeline

Gunnedah Shire Council Two (2) potable water reservoirs (Approximately 500kL each). Design and construction of approximately 15.8 kilometres of DN200 PVC-O Series 2 PN16 pipelines https://www.nvi.com.au/story/5781122/curlewis-pipeline-project-97-per-cent-complete/ https://www.prime7.com.au/news/5279-curlewis-pipeline-in-last-phase-of-construction
Fish River Water Supply Part Replacement of Stage 2 Pipeline

WaterNSWSeparable Portion 1 Separable Portion 2
Construction of Fish River Steel Pipeline

State Water Corporation Construction of 0.66 km long steel OD 914 – RRJ pipeline, 2.5 km long steel OD762 – RRJ pipeline, 0.6 km long steel OD762 welded pipeline, Scour valves, air valves and isolation valves, cross connections to Stage 1 and 3 pipelines (at two locations), Valve pits, thrust blocks, anchor blocks, supports, trench […]
Clarence Town Wastewater Transportation System

Hunter Water Corporation Completion of remaining works outstanding under terminated contract of former contractor for the construction of Clarence Town wastewater transportation system. Construction of sewer gravity system.Construction of 2 wastewater pump stationsConstruction of sewer rising mains. Many challenges were faced after the termination of the previous contractor. Community liaison was paramount to ensure the […]
Construction of Neath Watermain

Hunter Water Corporation Construction of 1,272m of 500mm DICL high pressure watermain.Construction of 66m of 300mm DICL watermain.
Veolia Amenities Building Remediation Toronto WWTP

Client: Veolia Water Operations Design and detail precast sleeper retaining wall at Toronto WWTP Excavation and piering of galvanised posts, install precast concrete sleepers, backfill retaining wall Minor grading works around the edge of the building to allow water to fall away from the structure Three months post construction, resin injection to level the building slab
Deep Sewer Contract T-08-01
Port Macquarie Hasting Council Supply and Construct – 650m 600Ø SewerMax 7m deep.
Eraring Poly
Maitland North Rothbury Water System Upgrade
Hunter Water Corporation Supply and Construct – 1347m 300 Dia DICL, 900m 375 Dia DICL and 2 Major Thrust Bores (New England Hwy, Wine Country Dr).
Muswellbrook Supply & Installation of Water Distribution Points at Denman & Muswellbrook

Client: Muswellbrook Shire Council Install two water dispensing units to allow access to bulk water 24 hours per day 7 days per week from convenient locations at Muswellbrook and Denman. Excavation of concrete slab and kerb at Denman and construction of new pipeline for both sites into the proposed water units. Installation of ancillaries including […]